SAMTEL Signs a ฿290Mn Contract with PEA to Install Power Transformation Monitoring System

SAMTEL Signs a ฿290Mn Contract with PEA to Install Power Transformation Monitoring System.


Samart Telcoms Public Company Limited (SAMTEL) has announced that “TD-STC Consortium”, which comprises SAMTEL and TEDA Co., Ltd. with the proportion of 50: 50, has signed the contract with PEA on March 31, 2021 for Installation of Power Transformation Monitoring System project with the total contract value of 290.20 million baht (VAT included) and portion for the Company values 145.10 million baht (VAT included). The project must be completed within 330 days from the next day after the contract signing date and the date that PEA delivers the areas to access for implementation. The project’s full amount of payment is divided into 4 payments based on work progress.